Projects

A heavy-duty, yellow track-type tractor with a black cab pulling a large soil compactor on a white background. The compactor is equipped with two massive metal rollers. The image suggests construction or land development.

The base on which progress is built.

Landpac caters to large-scale infrastructure projects in a wide range of industries. High Energy Impact Compaction (HEIC) is fundamental to our work in establishing key infrastructure assets such as shipping terminals, airports, and other transport networks. HEIC can make light work of land that other methods of compaction simply can’t touch – including reclaimed or otherwise inaccessible land – opening up new development and commercial opportunities.

Our work by numbers

5,381,881 km² of 
ground compacted

27 industries catered to

3 countries worked in

33,123,000 m3 of 
earth filled

91 clients collaborated with

139 projects delivered

And
counting!

Chek Lap Kok Airport

Location: Hong Kong
Client: Hong Kong Provisional Airport Authority

A construction site with two large yellow road rollers diligently advancing on a sandy terrain under a partly cloudy sky. These machines are actively working, leaving tracks as they tackle the ambitious project at hand.

Chek Lap Kok Airport was built on an airport platform (12.5 km²) with 75% of the area on reclaimed land with the remaining 25% formed by excavating two existing granitic islands. The construction comprised the placement of 197 million m³ with 70 million m³ of that being hydraulically placed dredged sand fill.

Landpac was engaged to carry out Impact Compaction of the in-situ sub-grade materials as an alternative to the costly removal to the required depth and backfilling in layers with conventional roller compaction.

Port Botany

Location: Sydney, NSW
Client: Sydney Ports

Aerial view of a large agricultural field with intricate tire track patterns; a lone tractor projects its vibrant color amidst earthy tones, diligently working at the center to cultivate the soil.

To achieve the required compaction in the hydraulically placed dredged fill to 16m depth or so, Dynamic Compaction or Vibro-Floatation was used. The upper 3m of the soil profile with the use of Dynamic Compaction or Vibro-floatation techniques on a non-cohesive soil tends to be loose. Impact Compaction provided an economical means of compacting the upper loose soil profile to the required compaction levels after the Dynamic Compaction or Vibro-floatation had been applied.

London Gateway

Location: London, UK
Client: Dubai Ports World

Aerial view of a bustling shipping port with numerous cranes and stacked shipping containers. In the foreground, construction projects are underway, with sandy areas dotted by equipment and vehicles. The horizon reveals a cityscape in the distance.

The London Gateway project consisted of land reclamation with dredged fill. Landpac was engaged to do the surface compaction of the upper 3m on Port 1 & 2 (16Ha) after the completion of the deep compaction.

Moin Container Terminal

Location: Costa Rica
Client: APM Terminals

A tractor moves across a large, barren construction site, where patterns of tire tracks crisscross the mud. Several cranes stand in the distance under a cloudy sky, silently witnessing the scale of the ambitious projects taking shape.

APM Terminals are expanding the port capacity at Limon Costa Rica, which handles 80% of the freight for Costa Rica. The terminal is being developed on a 40 Ha reclaimed area formed from dredged sand fill. Landpac has been engaged to compact the upper 3 metres to a Relative Density of 90%

Kooragang Island Coal Export

Location: Newcastle, Australia
Client: AbiGroup Construction

A large construction vehicle maneuvers over a grid-patterned dirt surface at a bustling construction site. With cranes towering and piles of dirt shaping the landscape, this ambitious project unfolds under a clear blue sky.

The NCIG Kooragang Island Project aimed to increase coal throughput capacity to 30 Mtpa, involving the dredging of three berths in the Hunter River’s south arm to construct a functional coal export port. This significant project saw the collaboration of Dredeco and Boskalis Australia in dredging, resulting in 3.5 million m³ of sands being repurposed as construction fill. 

Port Tanger Project

Location: Morocco
Client: Tanger Med Port Authority

A construction site near the sea buzzes with activity as a tractor and roller work on a large circular dirt area, contributing to ambitious projects. In the background, cranes and unfinished buildings rise under a clear blue sky.

The Tanger MED 2 project, a major container terminal development in Morocco, incorporated innovative compaction techniques for its 140ha construction site. Faced with the challenge of effectively compacting the top 2-3m of dredged material, a trial using Impact Compaction was executed.

Jebel Ali Port

Location: Dubai
Client: Dubai Ports World

Heavy construction machinery, including yellow steamrollers and graders, are seen on a vast dirt construction site under a cloudy sky. The equipment is positioned in a row, indicating active land development or roadwork.

At Jebel Ali Port, Dubai, a reclamation project behind Quay 4 and Berth 21 involved backfilling dredged marine sands to a depth of 16m, initially improved by Vibro compaction. However, initial Cone Penetration Testing indicated inadequate compaction in the top 2m. Landpac intervened, enhancing the bearing characteristics of this layer with their impact compaction technique.

Tuas Terminal Phase 1

Location: Singapore
Client: The Maritime and Port Authority of Singapore (MPA)

A barren field with two tractors diligently working the land under a cloudy sky, while in the background, an industrial complex projects its presence with large white buildings and multiple red-striped chimneys.

LANDPAC was engaged to do the surface compaction of the upper 2.4m sand fill layer to a 90%MMDD >1m depth and 95%MMDD ≤1m depth Compaction on the existing and newly reclaimed land by 410 ha. The compaction work was successively carried out by using a 3-sided twin drum impact compactor.

Planning for your next project?

Successful remediation of contaminated sites with HEIC

Landpac’s successful use of HEIC has been instrumental in significantly improving various contaminated sites, including:

Rail maintenance facility

A highly contaminated site with Asbestos Containing Materials (ACM) was stabilized using in-situ High Energy Impact Compaction (HEIC), followed by the placement of an orange geofabric barrier and a 20-inch (500mm) cap of clean Virgin Excavated Natural Material (VENM) for safety and compliance.

Smelter

The site, initially covering 130,000 square meters, was contaminated with heavy metals including lead, zinc, and arsenic. It underwent in-situ compaction using High Energy Impact Compaction (HEIC) as a remediation strategy. Following treatment, the area was expanded to 150,000m², capped, and repurposed for industrial use.

Defence facility

A specialised cell was constructed to contain Per-and Poly Fluoroalkyl Substances (PFAS)-contaminated soils, which were compacted on-site. This containment is crucial due to the persistence, environmental prevalence, and significant health impacts of PFAS contaminants.

Industrial development

A heavily contaminated 80,000m² site with ACM and heavy metals was rehabilitated using High Energy Impact Compaction (HEIC). After in-situ compaction and capping with approved materials, the site was transformed into a valuable industrial asset and sold to the client.

Latest news​

A green tractor with a yellow attachment is parked on a large, dusty field under a clear blue sky, ready for proof rolling. Trees and a few buildings are visible in the distant background.

Understanding High Energy Impact Compaction (HEIC)

High Energy Impact Compaction (HEIC) revolutionizes ground improvement with its ability to achieve superior soil density and stability. Unlike traditional methods, HEIC uses advanced rollers and compaction technology to penetrate deeper soil layers, addressing heterogeneities and enhancing load-bearing capacity. Ideal for mining, dredging, and large-scale earthworks, HEIC reduces project timelines, lowers costs, and promotes sustainability. Discover how Landpac’s innovative solutions deliver efficient and environmentally responsible results for heavy-duty projects.

Read More

Planning for your next project?